The Supreme Court has held that a power generator must bear transmission charges for two grid links it used while its own dedicated transmission line was delayed. The Court set aside the orders of the Appellate Tribunal for Electricity (APTEL) and restored the Central Electricity Regulatory Commission’s (CERC) tariff order for the links on the Tuticorin–Madurai transmission network.
The bench of Justices J.B. Pardiwala and K. Vinod Chandran found that the two links, known as Line-In Line-Out (LILO) connections, formed part of the approved transmission plan and carried electricity generated by Moxie Power Generation Limited, formerly Coastal Energen Private Limited. The dispute before APTEL concerned ₹15,43,26,909 in transmission charges outside the Point of Connection (PoC) sharing mechanism.
Buy Now: 90+ Supreme Court Judgments E-Magazine – October 2026
How the generator’s power reached the grid
Coastal Energen was responsible for building a dedicated transmission line from its generating station to the Tuticorin Pooling Station. While that line was pending, it used a temporary connection to feed power into one circuit of the existing Tuticorin JV–Madurai line.
Power Grid Corporation of India Limited had separately built two permanent LILO connections, one on each circuit of the same line. Once commissioned, the links diverted electricity through the Tuticorin Pooling Station before it continued towards Madurai. The first link entered commercial operation on January 4, 2015, and the second on January 8, 2015. The generator’s dedicated line became operational on October 27, 2016.
Network diagram showed both links carried power
APTEL had concluded that electricity from the generator travelled directly towards Madurai without passing through the pooling station. The Supreme Court examined the network diagram and found that the two links routed the electricity through the pooling station and then back onto the Tuticorin JV–Madurai line for onward transmission.
The Court also found that a delay in completing a separate connection from Tuticorin to Salem and onward to Madhugiri did not prevent the two links from carrying the generator’s power. It held that APTEL had relied on a paragraph of the CERC order that recorded TANGEDCO’s submissions, while the regulator’s findings placed liability for the charges on the generator.
Commercial operation dates stand
The Supreme Court held that APTEL had erred in directing the CERC to reconsider the commercial operation dates under Regulation 4(3)(ii) of the 2014 Tariff Regulations. The CERC had already accepted the dates for both assets. The record included certification from the Regional Load Despatch Centre following successful trials and a safety certificate from the Central Electricity Authority.
The restored order allows the two links to be included in the transmission tariff as non-PoC charges from their respective commercial operation dates until the generator’s dedicated line became operational on October 27, 2016.