The Bengaluru Bench of the Goods and Services Tax Appellate Tribunal (GSTAT) has confirmed a ₹1,00,20,488 GST demand and an equal penalty against a Hubballi-based works contractor for failing to declare and pay GST under reverse charge on mineral royalty deducted from its government contract bills and also directed payment of interest under Section 50.
The bench of Prabhakaran P.M. (Judicial Member) and Ravi Jesuraj S. (Technical Member (State)) allowed the department ’s appeal and overturned the first appellate authority’s decision to apply Section 73 and impose a 10% penalty. The GST levy and the amount of tax were outside the scope of the appeal. The dispute concerned whether the evidence established suppression with intent to evade tax, bringing the demand within Section 74 of the Central and Karnataka GST Acts.
Buy Now: All 200+ GSTAT Judgements Till November 2026 | Comprehensive E-Magazine
The bench noted that a government works contractor’s repeated omission of mineral royalty from its GSTR-3B returns, together with evidence of its knowledge of the levy and its conduct after detection, established suppression to evade GST under Section 74.
The firm executed government works contracts for roads, dams, reservoirs and bridges. Its clients included the Karnataka Urban Water Supply and Drainage Board and the Public Works Department. The departments calculated royalty on minor minerals such as gravel, murrum, rock fill and sand used in the works and deducted the amounts from running-account bills. In one bill alone, the Water Supply and Drainage Board deducted ₹37,52,549.
Between July 2017 and October 2019, the departments deducted ₹8,86,04,082 in royalty. The contractor entered the deductions in its ledgers as royalty paid to the government. Its monthly GSTR-3B returns for July 2017 through September 2019 omitted the corresponding reverse-charge liability.
The preventive unit first sought records on September 20, 2019, and issued a summons on October 11. The contractor produced its royalty ledgers, returns and sample bills on November 14. Six days later, it paid ₹46,37,250 in tax for April to October 2019. The payment excluded interest and left the tax for July 2017 to March 2019 unpaid.
The first appellate authority accepted that the contractor had suppressed the transactions but found the evidence insufficient to establish an intent to evade tax. It therefore confirmed the demand under Section 73. The tribunal held that the statutory definition of suppression and the question of intent required separate findings. Explanation 2 to Section 74 covers both the omission of information required in a return and the failure to furnish information sought in writing by the proper officer. The contractor’s cooperation during the inquiry addressed the latter. The earlier return omissions still had to be assessed. The burden of establishing intent remained with the Revenue.
The bench drew its inference from three circumstances. The firm knew of the deductions because they arose under its own contracts and appeared in its ledgers. Its General Manager (Accounts), who oversaw GST returns and payments, acknowledged the reverse-charge levy on licensing services for the right to use minerals, while disputing whether the firm received such a service. The tribunal also referred to Serial No. 5 of Notification No. 13/2017–Central Tax (Rate), which places the payment obligation on the business recipient for specified government services.
The tribunal treated the repeated filing of returns omitting the royalty liability as a positive declaration under the GST self-assessment system. It found no contemporaneous disclosure of the transactions or of the firm’s position to the proper officer. It then considered the timing and scope of the partial payment alongside those earlier omissions. The General Manager said the firm paid for seven months to narrow the dispute and because it expected to claim input tax credit. The tribunal made clear that a payment after detection, viewed on its own, is insufficient to establish intent.
The bench also found that the show-cause notice set out the relevant allegations, including the omission from the monthly returns, the failure to self-assess the tax and the discovery of the default during investigation. The firm had addressed those allegations in its replies.
The contractor argued that it held no mining lease, obtained materials from licensed suppliers and faced deductions that merely recovered royalty unpaid by miners. The tribunal noted that the government departments charged royalty under the firm’s own contracts and recovered it from the firm’s bills. The contractor had recorded those amounts as royalty paid to the government. The bench considered the argument as an explanation for the firm’s conduct, given the limited scope of the appeal.
The tribunal found that the firm first advanced its argument that royalty was itself a tax in its reply to the show-cause notice, more than a year after detection. It also noted that the October 2021 CBIC circular on the applicable royalty GST rate came after the disputed period and the notice. The bench found no evidence that either issue had informed the firm’s decision to omit the transactions during the relevant years.
The bench rejected the revenue-neutrality defence based on potential input tax credit. It referred to Section 17(5)(i) as it stood during the disputed period, which blocked credit for tax paid under Section 74. The possible availability of credit in the ordinary course did not establish that the omissions were innocent.
| Particulars | Tribunal’s direction |
| GST demand for July 2017 to October 2019 | ₹1,00,20,488 under Section 74(1), split equally between CGST and Karnataka GST |
| Payment made on November 20, 2019 | ₹46,37,250 to be credited against the tax demand |
| Balance tax after crediting payment | ₹53,83,238 |
| Interest under Section 50 | Payable from the respective monthly due dates. Interest on the ₹46,37,250 already paid runs up to November 20, 2019 |
| Penalty under Section 74(9) | ₹1,00,20,488, replacing the penalty under Section 122(2)(b) in the original order |
The tribunal held that the firm’s partial pre-notice payment did not qualify for the benefit under Section 74(5), which required payment of the tax, interest and a 15% penalty. It also excluded the original adjudicating authority’s observation about a 25% penalty under Section 74(8), since the 30-day window after issue of the notice had already elapsed. Applying Section 75(13), the bench directed that only one penalty be imposed for the same default. It made no order as to costs.
Membership Required to Access Case Details & Order Copy